ENVIRONMENTAL DEVELOPMENT GROUP LIMITED v. PROVIDENT INSURANCE CO. LTD. & ANOR
March 18, 2020
SUPREME COURT
GHANA
CORAM
- BAFFOE-BONNIE, JSC (PRESIDING)
- PWAMANG, JSC
- MARFUL-SAU, JSC
- DORDZIE (MRS), JSC
- KOTEY, JSC
March 18, 2020
SUPREME COURT
GHANA
CORAM
Try asking the following...
PWAMANG, JSC:-
My Lords, this case comes before us as the final appellate court of the Republic. The case stems from an agreement made on 26th June, 2003 by which the plaintiff/respondent/respondent (the plaintiff) undertook to build two hostels at Tamale Polytechnic for the 3rd defendant/appellant/appellant (3rd defendant). The plaintiff is a building contractor and the 3rd defendant is an agency of the Government of Ghana in charge of providing facilities for educational institutions among other functions. The agreement was comprehensive and spelt out the rights, duties and obligations of all the parties and stated what should happen in the event of, practically, all the known contingencies in construction projects. The agreement provided for a dispute resolution mechanism for industry experts to arbitrate any dispute that may arise. Despite all this, the parties ended up in court and the case has taken fifteen years to be brought to closure.
The facts of the case are largely documentary and its resolution ought to have consisted in applying the detailed provisions of the agreement to the facts and arriving at a decision which, in our opinion, should have taken far less judicial time than happened in this case. Also, if the alternative dispute resolution mechanism provided for in the agreement had been applied, the controversies regarding the technical aspects of the case would have been resolved by building industry experts so that any outstanding issues of pure law could then have been brought to the courts for determination. However, for reasons that do not concern us in this appeal, the court refused to grant an application for reference of the case for arbitration. But it ought to be stated, that from the record, a considerable amount of the time was used up by the parties to attempt settlement and for valuation of the works executed before the dispute arose.
My Lords, in the agreement, the cost of building the two hostels in today’s Ghana Cedis is GHS1,388,763.80 (Thirteen Billion, Eight Hundred and Eighty Seven Million, Six Hundred and Thirty Seven Thousand, Nine Hundred and Fifty Eight Cedis, Fifty Two Pesewas at the time). The contract period was fixed at eighteen months within which the plaintiff was to practically complete and hand over the works as set out in detailed drawings. There was however a provision for extension of time to be granted to the plaintiff if certain stated conditions outside the control of the plaintiff occurred and ca
AI Generated Summary
The Supreme Court of Ghana, per Pwamang JSC, resolved a long-running construction dispute arising from a 2003 contract to build two hostels at Tamale Polytechnic. The Court reframed the case around a crucial overlooked issue: whether the contract was still binding on 8 April 2005 given the 18-month completion period had expired with no explicit extension under Clause 19. Interpreting Clause 19s shall as mandatory, and requiring impartial decision-making by the Contract Administrator, the Court found documented excusable delays but concurrent contractor delay. The failure to grant a fair and reasonable extension was a fundamental breach, entitling the contractor to treat the contract as discharged; nonetheless, speculative special damages and quantum meruit were not proved. Applying the prevention principle and Clause 18 certification, liquidated damages were unavailable, so the surety was restrained from paying on the bonds. The employers counterclaim was dismissed, lower court judgments set aside, and general damages of GHS70,000 awarded.