DE SIMONE LTD vrs OLAM GHANA LTD
May 8, 2025
COURT OF APPEAL- (CIVIL DIVISION)
GHANA
CORAM
- G. S. SUURBAAREH, JA (PRESIDING)
- N. A. ARYENE (MRS.), JA
- DR. OWUSU-DAPAA, JA
May 8, 2025
COURT OF APPEAL- (CIVIL DIVISION)
GHANA
CORAM
Try asking the following...
[1]. This appeal arises from a construction contract between De Simone Ltd (“the Appellant”), a civil engineering and construction firm, and Olam Ghana Ltd (“the Respondent”), a company incorporated under the laws of Ghana. Under the terms of the agreement dated 15th December 2011, the Appellant undertook to design and construct a Wheat Mill factory for the Respondent at Kpone, Tema, for the fixed price of US $12,000,000.00. Disputes emerged when the Respondent failed to pay various progress claims and continued to direct additional works and variations to the scope of the project. In the High Court, the Appellant’s amended writ of summons and statement of claim filed on 7th February 2019 sought:
(a) An order for payment by the Respondent of US $8,202,687.71, representing the aggregate value of works performed, loss of profit, and cost overruns incurred by the Appellant; and
(b) Interest on that sum from 30 June 2012 until the date of final judgment.
[2]. The Respondent denied liability to pay the sums claimed and, by its further amended statement of defence and counterclaim filed on 22 May 2019, counterclaimed against the Appellant for:
(i) General damages for breach of contract;
(ii) The sum of US$12,512,000.00, calculated at US$16,000.00 per day of delay in handing over certain foundations, buildings, and utilities; and
(iii) Costs of the counterclaim.
[3]. By their Further Amended Statement of Claim filed on 7th February 2019, the Appellant (formerly “the Plaintiff”) avers that on 8th December 2010, they entered into an agreement with the Respondent (formerly “the Defendant”) for the construction of a Wheat Mill factory at Kpone, Tema, for a total sum of US$12,000,000. Under the terms of the agreement, various sections of the factory were to be completed and handed over by agreed dates. The entire factory, however, was to be completed by the Appellant within 311 days—on or before 15th October 2011.
[4]. The Appellant contends that while they completed and handed over the Mill and Warehouse buildings in February 2012, the remainder of the factory was handed over on 31st May 2012. This was 229 days after the original agreed completion date of 15th October 2011, although the Respondent allegedly commissioned and started using the factory in February 2012. The Appellant maintains that the delay in completing the remainder of the factory was attributable exclusively to the Responden
AI Generated Summary
The Court of Appeal of Ghana adjudicated a dispute between De Simone Ltd and Olam Ghana Ltd arising from the construction of a wheat mill factory at Kpone, Tema, under a US$12 million contract incorporating FIDIC-based provisions. The High Court had found concurrency of delays, awarded De Simone about US$2.33 million on its claims and Olam about US$2.56 million in delay damages, and set off to leave a net US$234,000 to Olam. On appeal, the panel (G. S. Suurbaareh JA, N. A. Aryene JA, and Dr. Owusu-Dapaa JA) struck out defective grounds under C.I. 19 and reviewed key issues: apportionment of delay responsibility, the existence of a purported US$1.2 million cap tied to the performance bond, enforceability of daily liquidated damages, appropriate treatment of concurrency, and Olams request to stack milestone damages. The Court modified the apportionment to 60% employer and 40% contractor, rejected any cap, upheld the daily rates, affirmed the cumulative approach to avoid double-counting, awarded full retention to De Simone, fixed the contractors delay damages at US$1,465,600, and ordered a net payment of about US$1,037,402.44 to De Simone with interest.