SIKAPRESS MICRO-CREDIT LTD vs. CHARLES OPPONG ASARE & ANOR
June 24, 2026
HIGH COURT
GHANA
CORAM
- ISAAC ADDO, J.
Areas of Law
- Contract Law
- Evidence Law
June 24, 2026
HIGH COURT
GHANA
CORAM
Try asking the following...
This case invites the Court to distinguish between the shadow and the substance. The Defendants contend that the debt in question belongs to a corporate entity, whereas the Plaintiff’s case states the contrary. In the theatre of commerce, one cannot play the part of the principal borrower and, upon the fall of the curtain, claim to have been merely a director of a non-participating entity.
The Plaintiff, a limited liability company caused to be issued at the Registry of this Court, a Writ of Summons and Statement of Claim on the 9th September, 2020 seeking the following reliefs against the Defendants jointly and severally:
a. An order for the recovery of GH¢448,000.00 being the amount outstanding on a loan facility granted 1st Defendant in August, 2019 and the repayment of which was guaranteed by 2nd Defendant.
b. Interest to be calculated on the said amount at the agreed rate of 4% per month from 16th February, 2020 to the date of final payment.
c. A penal fee of 1% per month to be calculated on the GH¢448,000.00 from 16th February, 2020 to date of final payment.
d. Cost including cost of litigation.
The Defendants entered Appearance through their lawyers on the 3rd November, 2020 and filed their Statement of Defence on the 4th February, 2021 denying liability of all the claims of the Plaintiff.
The Plaintiff is a micro-credit company incorporated under the laws of Ghana and licensed by the Bank of Ghana to provide micro-credit services. Sometime in August, 2019, the 1st Defendant applied to be granted a loan facility of GH¢400,000.00 for the purpose of clearing goods from the Port. The facility was granted for a period of six (6) months and at an agreed interest rate of 4% per month with repayment commencing sometime in September, 2019. The parties agreed to a penal fee of 1% per month in the event of default. The 1st Defendant secured the loan facility with a land lying and situate at New Weija, a suburb of Accra in the Greater Accra Region. In addition to the land, the facility was secured with a Toyota Tundra vehicle. The repayment of the loan facility was also guaranteed by the 2nd Defendant personally. At the end of the transaction period being the 16th February, 2020, the 1st Defendant was expected to repay GH¢448,000.00 comprising the loan principal and interest but failed to do so. Notices of default of 1st Defendant has been brought to the attention of Defendants but the
AI Generated Summary
SIKAPRESS MONEY LENDING COMPANY LIMITED sued Charles Oppong Asare (1st Defendant) and his wife, Faustina Serwaa Sarpong (2nd Defendant), to recover an unpaid micro3credit loan tied to a six3month facility issued in August 2019. Asare argued the debt was owed by Foresight International Company Ltd, where he and Sarpong are directors, and tendered an 3Acknowledgement4 referencing receipt on the company4s behalf. The Court examined the Loan Agreement naming 3CHARLES OPPONG ASARE (Trading as Foresight International Company Ltd)4 as the borrower, his unqualified signature, the guarantor4s undertaking expressly referencing Asare4s indebtedness, and a statutory declaration pledging his personal land and Toyota Tundra as collateral. Applying contract interpretation precedents, the parol evidence rule, estoppel by conduct, and burdens under the Evidence Act, the Court held the facility was a personal loan to Asare, guaranteed by Sarpong. Payments totaling GH48,000 were made during the facility period and GH10,000 later, leaving GH448,000 due as at 16 February 2020. Judgment entered jointly and severally for the plaintiff, with 4% monthly interest and 1% penalty from default, and GH10,000 costs, noting counsel4s failure to file addresses did not affect adjudication.