Eskwai logo
Verify now as a student, judge or newly called lawyer for access to discounted plans.

J. ADDISON & CO. LTD v. THE MINISTER, MINISTRY OF EDUCATION & THE ATTORNEY-GENERAL & MINISTER OF JUSTICE

July 20, 2016

HIGH COURT

GHANA

CORAM

  • JENNIFER DODOO (MRS) JUSTICE OF THE HIGH COURT

Areas of Law

  • Contract Law
  • Evidence Law

AI Generated Summary

This High Court judgment arises from a construction payment dispute between a limited liability company that built a two‑storey dormitory for Benkum Senior High School and the Ministry of Education as employer. The company alleged late payment on several interim payment certificates and sought GH¢63,605.17 in interest under clause 43.1 and GH¢18,458.29 as the final balance, plus damages linked to indebtedness to Sahel‑Sahara Bank and Unibank. The court examined the contract’s certification regime and evidence from the Project Manager’s quantity surveyor, finding that interest is not automatic and must be requested and certified by the Project Manager. The Plaintiff failed to lodge formal, contemporaneous claims with the Project Manager and relied on an unauthenticated calculation (Exhibit F) that did not satisfy evidentiary standards. The court held the Plaintiff had not proven entitlement to interest or the final balance, dismissed all claims, and awarded GH¢10,000 costs against the Plaintiff.

JUDGMENT