DESHINA BUILDING WORKS LTD. v. BUAH
June 28, 1979
HIGH COURT
GHANA
CORAM
- ANSAH-TWUM J
Areas of Law
- Contract Law
- Civil Procedure
- Property and Real Estate Law
June 28, 1979
HIGH COURT
GHANA
CORAM
Try asking the following...
JUDGMENT OF ANSAH-TWUM J.
The plaintiff's claim against the defendant is for the sum of ¢28,021 which is set out as follows:
"(a) ¢18,000 being the balance or damages or both due on a building contract between themselves and the defendant and which the defendant unilaterally terminated; and,
(b) the sum of ¢10,021 being the cost of building materials belonging to the plaintiff company and which the defendant collected from the site of operations at the time he terminated the contract."
In his pleading, the defendant denied liability and pleaded further that the original contract price was ¢100,000 but was later on [p.393] mutually varied upwards to ¢120,000 because of a rise in prices of materials at the time, and he paid thereon a total of ¢102,000. The defendant continued in paragraphs (4), (5) and (6) of his statement of defence:
"(4) The defendant says that for no apparent reason the plaintiffs thereafter abandoned work on the defendant's building and in spite of the defendant's protestations the plaintiffs failed to continue.
(5) The defendant further says that at the time the plaintiffs abandoned the project it was incomplete and haphazard.
(6) In desperation the defendant turned to Messrs. Ahey Ltd. who agreed to complete the work at an additional cost of ¢135,000."
The plaintiffs joined issue in their reply with the defendant on his defence generally and admitted that the original contract price was eventually varied upwards to ¢120,000 because of additional jobs they were to carry out on the building. The plaintiffs did specifically deny paragraphs (4) and (5) of the statement of defence to the effect that they did themselves abandon work on the defendant's building. The most important issues which were thus set out for trial are:
"(b) Whether the plaintiffs abandoned the building operations for the defendant for no good cause.
(c) Whether or not the materials collected by the defendant are for the plaintiffs.
(d) Whether or not the plaintiffs are entitled to the relief sought."
The defendant also counterclaimed for damages for breach of contract against the plaintiffs.
The plaintiffs were represented in this action by David Eshun, who signed himself as the managing director of the plaintiff-company on the written contracts and other relevant documents tendered in evidence in this matter. The plaintiffs' evidence is that they entered into a building contract with the defendant to construct, originally, a two-storey building for the
AI Generated Summary
This case concerns a building contract between a plaintiff construction company, represented by managing director David Eshun, and defendant A. K. Buah for a multi-storey residence in Takoradi. Two written agreements (exhibits A and B) set the work and price, which was later varied from ,000 to ,000 due to additional work and rising costs; Buah paid ,000. Plaintiffs maintained that delays resulted from Buah refusal to promptly release funds and his undertaking to perform terrazzo flooring, which impeded completion. While plaintiffs were still working, Buah engaged Ahey Ltd. to finish the job and, on 23 January 1978, sent a termination letter and seized materials valued at ,021. The court found plaintiffs had not abandoned the project; time ceased to be of the essence due to defendant-caused delays. Applying building-contract principles and damages doctrine, the court held Buah breached the contract, awarded ,000 general damages and ordered return of ,021 for seized materials, dismissing Buah counterclaim with costs.