March 23, 2023
HIGH COURT OF JUSTICE
GHANA
CORAM
By a writ of summons, the Plaintiff on 21/11/2017 instituted an action against the Defendant herein for the following reliefs:
(a) General and special damages for breach of contract.
The writ was accompanied with a statement of claim where the Plaintiff, a limited Liability Company in Ghana, upon a proposal on the Management of the Jubilee Park in Takoradi, a property of Defendant Metropolitan Assembly was requested to manage the Jubilee Park (facility) on a pilot basis for 1/1/2014 to 31/12/2014 so as to assess the possibility of the project before the parties could bind themselves by a formal agreement and the agreement was evidenced in writing providing the details of the pilot project. According to the Plaintiff, the project was extended for 1/1/2015 to 1/12/2015 by a short agreement and this was done.
The parties, according to the Plaintiff then in 2016 engaged each other for a deal resulting in a Build-Operate-Transfer Agreement (BOT) where upon the Plaintiff sourced for some financial facilities to commence work as it was Capital-intensive. But in May 2017 the Defendant wrote to the Plaintiff to hold on for further constructional works but 3 days later, the Defendant wrote to terminate the contract unilaterally. This, according to the Plaintiff is unlawful and so he caused his lawyers to write to the Defendants on the work done on the facility and also the cost incurred and demanded his money. But this was not needed to hence the instant suit to demand damage and breach of contract.
The Defendant admitted having put out a notice for proposals for the private management of the Jubilee Park and requesting applications but vehemently denied having entered into any contract with the Plaintiff on working on the facility on pilot basis.
The Defendant however admitted entering into a contract with the Plaintiff on BOT basis and added that prior to the execution of the agreement, the Plaintiff had represented to the Defendant that he had the requisite financial and technical resources to undertake the project. The Defendant admitted writing to the Plaintiff to hold on with the project because of fundamental breaches of the contract of the Plaintiff.
The Defendant states that the breaches included the inability to execute the project envisaged in the agreement within the agreed duration of 10 months and the refusal or failure to make out certain payments to the Defendant. The Defendant wrote to terminate the agreement and admitted also rece
AI Generated Summary
This Ghana High Court judgment involves a Build-Operate-Transfer contract between Sekondi-Takoradi Metropolitan Assembly and Black Child Company Ltd. After two successful pilot management phases of Jubilee Park, the parties executed Exhibit C on 14 September 2016, obliging the company to rehabilitate the facility over a 10‑month construction period, submit a performance bond in the 10th month, and provide proof of financing. Black Child Company began rehabilitation in September 2016, financing works through bank loans and reporting progress. In April/May 2017, the Assembly’s engineer orally directed suspension; three days after a letter (Exhibit G), the Assembly terminated (Exhibit H) without written notice to rectify or the required three‑month notice. The Assembly’s valuation (GH¢51,153.50) and part payment (GH¢40,000) were disputed. Applying Ghanaian authorities on termination, certainty, and damages, the Court found no fundamental breach by Black Child Company and held the termination unlawful, awarding special damages (GH¢64,050) and nominal damages (GH¢50,000), for a total of GH¢114,050 plus costs (GH¢15,000).