AUGUSTINA ENGMANN v. PELICAN GROUP LTD

2018

HIGH COURT

GHANA

CORAM

  • ERIC K. BAFFOUR ESQ.

Areas of Law

  • Contract Law
  • Property and Real Estate Law
  • Civil Procedure

AI Generated Summary

The Plaintiff and Defendant entered into a lease for developing land into residential units, but the Defendant's lack of construction progress led to a breach of contract claim. The Defendant cited permit issues from the A.M.A and other technical difficulties as reasons for delay. The court determined that the Defendant had indeed breached the contract terms, ordering the reimbursement of the building's replacement value and the transfer of the land title back to the Plaintiff. Additional awards included mesne profits, general damages, and costs for Plaintiff owing to the Defendants failure to comply with the contract terms and regulations.

JUDGMENT