Zhoushan Jinhaiwan Shipyard Co Ltd v Golden Exquisite Inc
December 5, 2014
COMMERCIAL COURT
United Kingdom
CORAM
- MR JUSTICE LEGGATT
Areas of Law
- Contract Law
- Civil Procedure
December 5, 2014
COMMERCIAL COURT
United Kingdom
CORAM
Try asking the following...
Judgment
Section Para No. Introduction 1 The contracts 2 The disputes 6 The arbitration awards 11 The appeals 16 Approach to interpretation 22 The contractual scheme 27 Buyer’s breach delays 36 The right to cancel under Article VIII.3 40 The presumption against the Buyer benefiting from its own breach 45 Were the alleged delays ‘”permissible” delays? 57 The effect of failure to give notice of delay 63 Conclusion on cancellation 71 Equitable set-off 72 Conclusions 78
Mr Justice Leggatt :
Introduction
These four appeals from arbitration awards raise questions of interpretation of the cancellation provisions in four materially identical shipbuilding contracts. The vessels which are the subject of the contracts are known by their respective Yard Hull numbers: J0051, J0052, J0119 and J0120. In each case the contract was made between Zhoushan Jinhaiwan Shipyard Co Ltd of the People’s Republic of China (“the Yard” or “the Builder”) and a buying company specially created for that purpose (“the Buyer”) which formed part of the Golden Ocean Group. In each case the Buyer has purported to exercise a contractual right to cancel the contract on account of delay in delivering the vessel. In each case the Yard has sought to argue that the cancellation was wrongful on the ground that a relevant part of the delay was caused by the Buyer’s own breach of the contract. The central question raised by these appeals is whether the factual allegations made by the Yard as to the extent and cause of delay, if proved, provide an answer to the Buyers’ claims, or whether on the proper interpretation of the contracts the cancellations were lawful even on the facts alleged.
The contracts
Article I of each contract contained a description of the vessel to be built. Article II specified the contract price of the vessel and provided for the price to be paid by the Buyer in five instalments, with the final instalment due upon delivery of the vessel. Article III provided for the contract price to be adjusted in various circumstances. Relevantly for present purposes, Article III.1(b) required the contract price to be reduced by deducting US$7,000 from the final instalment for each day that the delivery of the vessel was delayed by more than 30 days but less than 210 days after the Delivery Date specified in Article VII. Article III.1(c) gave the Buyer a right to cancel the contract if the delay in the delivery of the vessel continued for a period of at least 210 days. This right was expr
AI Generated Summary
Mr Justice Leggatt determines four appeals from London arbitration awards concerning cancellation rights in materially identical shipbuilding contracts between Zhoushan Jinhaiwan Shipyard Co Ltd and special-purpose Buyers within the Golden Ocean Group. The Buyers cancelled after delivery was delayed well beyond the Delivery Dates; the Yard argued the delays were caused by the Buyers’ supervisor’s breaches of Article IV and thus should not count towards cancellation thresholds. Interpreting the contract as a tripartite scheme of permissible, non‑permissible, and excluded delays, the court holds Article IV breaches do not extend delivery and, even if arguendo within Article VIII.1, the Yard’s failure to give Article VIII.2 notice means no relief. The delays were non‑permissible and counted towards both Article VIII.3 and Article III.1(c) thresholds, making cancellations valid and interest payable. Equitable set‑off was rejected; the Yard’s appeals were dismissed, with Buyers’ interest appeal allowed for J0051/J0052 and J0119/J0120 affirmed.